久久精品国产亚洲一区二区 I 欧美成人精品高清视频 I 国产精品水嫩水嫩 I 国产精品自拍视频网站 I 西班牙黄色片 I 欧美色欧美亚洲日韩在线播放 I 亚洲国产成人综合 I 伊人色综合网 I 亚洲理论电影在线观看 I 国产五级片 I 午夜免费av I 8x国产精品视频一区二区 I 美国久久毛片 I 日本成人一级片 I 亚洲色图日韩 I www欧美激情 I 最近更新中文字幕 I 亚洲一卡一卡二新区无人区 I 亚洲国产精品无码久久久不卡 I 自偷自拍视频 I 超碰1000 I 亚洲不卡高清视频 I 人人妻人人做从爽精品 I 黄色影视网站 I 国产视频在线观看网站 I 久久图片视频 I 欧美欲妇 I 中文字幕成人在线 I 麻豆日韩精品 I 激情偷拍视频 I 欧美三级一区二区三区 I 国产艳俗歌舞表演hd I 河北彩花中文字幕 I hd极品free性xxx护士 I 老司机成人在线视频

Welcome to Weifang Zhiyang Machinery Co., Ltd. official website!

Hotline:+86 18953666083

LBS

How to deal with the inconsistency of the determination of the reference volume of the concrete mixing plant?

period:2018-03-22 14:30:08 Clicks:

The focus of the dispute between the two parties is on the amount of concrete. The key is how to use the value of the reference amount of concrete to go to the top. Now there are two commonly used benchmarks. The first is based on the theoretical volume calculation of the construction drawings, which is the so-called settlement by drawing. The second is based on the calculation of the concrete company's volume of supply volume, which is the so-called shipping ticket settlement. These two different methods for calculating the amount of squares each have their own drawbacks, thus causing uncertainty in the determination of the actual amount of data.

First, according to the theoretical basis of the volume of calculation of the construction drawings

This method is beneficial to the demand side and unfavorable to the supply side. The construction unit has professional technicians to calculate the volume of the components, and the concrete mixing station will not configure the corresponding professionals to do the drawing calculations. In addition, the changed part of the drawings may not be counted, and it is not excluded that the construction unit intends to conceal it. According to the calculation of the amount of drawings, it should also be based on the as-built drawing, but the drawing of the Yuan Yuan lags behind the supply of concrete, and the operability is poor.

Second, according to the amount of volume calculated by the supplier of concrete mixing station records

This method is favorable to the supplier and unfavorable to the demander. The concrete mixing station uses the mixer truck as the supplier unit. Each vehicle carries a delivery order with the above indicated amount. Actually, the delivery truck is loaded with this value. In accordance with the concrete, the person responsible for signing at the construction unit has no way of knowing. If the concrete mixing plant wants to deliberately lose money, it is easy to do. ?